Development Costs
Estimate of Costs for Skyways Infrastructure |
||||
Guideway | ||||
148 Conc. Guideway Girders | 5200 | feet | 1,520,000 | |
Switches | 12 | 180,000 | ||
74 Columns | 10000 | each | 740,000 | |
74 Crossbeams | 7851 | each | 581,000 | |
Shipping and erection | 293,000 | |||
Footings at 15% of above costs | 453,150 | |||
Steel Roadbed track | 5200 | feet | 400,000 | |
Docking Ramps 12 x 250 feet | 3000 | feet | 600,000 | |
Stations at 3 pairs per mile | 3 | @ 500,000 | 1,500,000 | |
Operations and Maintenance Center | 1,500,000 | |||
Fuel depot | 300,000 | |||
Power Generation and Distribution | 1,200,000 | |||
Control System | 1,500,000 | |||
Vehicles (assume six to start) | 100000 | each | 600,000 | |
Construction | $11,367,150 | |||
General Conditions at 5% | 568,358 | |||
Kiosks | 40,000 | |||
Construction Contingency at 10% | 1,137,150 | |||
Engineering and Supervision at 15% | 1,640,430 | |||
Administration at 3% | 783,607 | |||
Total Costs | $15,536,695 | |||