Development Costs


Estimate of Costs for Skyways Infrastructure
Guideway
148 Conc. Guideway Girders 5200 feet 1,520,000
Switches 12 180,000
74 Columns  10000 each 740,000
74 Crossbeams 7851 each 581,000
Shipping and erection 293,000
Footings at 15% of above costs 453,150
Steel Roadbed track 5200 feet 400,000
Docking Ramps 12 x 250 feet 3000 feet 600,000
Stations at 3 pairs per mile  3 @ 500,000 1,500,000
Operations and Maintenance Center 1,500,000
Fuel depot  300,000
Power Generation and Distribution 1,200,000
Control System  1,500,000
Vehicles (assume six to start)  100000 each 600,000
Construction $11,367,150
General Conditions at 5% 568,358
Kiosks 40,000
Construction Contingency at 10%  1,137,150
Engineering and Supervision at 15% 1,640,430
Administration at 3% 783,607
Total Costs $15,536,695

 

 

 
 

Summary   |   Corporate   |   Technology   |   Routes   |   Market   |   Interact   |   Search

 
 

Alternative Transit | Personal Rapid Transit (PRT) | People Movers

 
 

Contact Us   |   Beyond Oil   |   Demonstration Model

 
 

Copyright © SmartSkyways, LLC. 2006. ALL RIGHTS RESERVED